Standup9ja: FG to terminate 6 abandoned projects in Niger
Delta
The Ministry of Niger Delta Affairs has concluded
arrangements to terminate about six abandoned projects spread across the region
with a view to enhance the development of the region.
Recall that the Minister, Pastor Uguru Usani had made this
known while receiving the report on the audit and review of the East-west road
and other project of its Ministry in Abuja.
Usani said that following the report from the Ministerial
Technical Audit Committee on the contracts awarded from 2009 – 2015 in the
Niger Delta, that some projects have been proposed for termination.
He listed the projects to include construction of
OkpuhutaMbano Junction – Orie market –Lomara- Igwebulka (35km) – Abia State;
Land reclamation and Erosion control project at OguduAbia Phase I, Abia State.
Others are Idoro-Eastern Itam Water Supply Scheme Akwa Ibom;
Construction of Mbak Atai-Ikot Ntu-MkpetiOkuiboku road project (13.86km) Akwa
Ibom State; Ukparam Water Supply Scheme and Construction and Supervision of
Omelema – Agada II Road, Rivers State. Project Length 14.415km.
The minister said the above listed projects were proposed
for termination as a result of lack of capacity to complete the work as
witnessed on site.
He said, “Gross lack of capacity problem, lack of
seriousness on the project, lack of technical capacity to prosecute project and
gross lack of competence by the contractors.
Usani said the committee juxtaposed its findings from
project sites against facts retrieved from available documents domiciled in the
departments that supervised the projects.
According to him, there were violation of contract award
process; Right from the cycle of procurement planning to contract award, the
committee noticed inconsistencies with the provisions of vital aspects of the
Procurement Act.
“Prominent among other issues of violation were indiscriminate
award of contract by initiating and benefiting departments without the leading
and guiding role of the procurement department.
“Awards never took cognizance of availability of funds and
annual appropriation provisions,” he said.
The minister said the structure and content of some contract
agreements lack checks and balances, saying that they hardly protect the
interest of the Ministry in case of disputes.
He explained that the imminent picture of abandoned and
uncompleted projects was as disturbing as the retinue of projects that
extremely exceeded the dates of completion.
“This manifestly, emanated from inconsistency in government
annual budgetary provision and lack of capacity to deliver especially where
funds released do not correspond with performance.
“Most contracts were awarded with specific dates of
completion but were not captured in subsequent appropriations.
According to the minister, this further exacerbated
contractors’ poor performance and inability to achieve project objectives.
“Consequently, no capital project was completed within the
stipulated time frame,” he said.
Mr Chijoke Micheal, an Estate Manager, from Abia State, told
NAN that the policy of terminating contracts not executed by contractors would
speed up development in the Niger Delta region.
“Those contractors who think they can eat their cake and
have it should better sit up because the present administration is determined
to develop the region and curb corruption.
“We have been advocating for this change for a long time and
I have been very vocal in calling on government to come down to our level and
assist the region in development.
Micheal said: “It is important for contractors to realize
that it can no longer be business as usual.
“It is important for everyone doing business with the
ministry to realize that things must be done properly,” he said.
Mrs Emen Odok an architect from Cross River described the
policy as a waste of money, saying that government want to politicize it, by
putting such policy in place.
“What is wrong with the government calling the contractors
to order? The excuse by the ministry doesn’t hold water at all.
“Rather than terminate a project that is 45per cent
completed, why not terminate the contract and re-award the contract to another
company that is most capable of completing it.
“The ministry has practically abandoned the Calabar skills
acquisition centre, these beautiful structures are wasting away and being
destroyed by erosion.
“What measures has the government put in place to address
such wastage,” she said.
Mr Okon Udoh, a retired Civil servant, said the ministry has
so many abandoned projects spread across the region, saying that the Federal
Government should address the issue, if truly government wants to develop the
region. (NAN)